How Is Magic Works​

Projects of Zagros Sanat Arka Company

1

Discharging and charging reactors of desulfurization unit

Client: Saba Steel Isfahan

Project implementation time frame: 3 days

Start date: 5/20/98

Location: Mubarke, Isfahan

www.msc.ir

2

Overhaul of the reformer unit includes: discharging and charging the catalyst, cutting and welding the doglegs, opening and closing the suspension systems, opening and closing the switch tubes, cleaning the tubes.

Client: Saba Steel Isfahan

Project implementation period: 15 days

Start date: 8/4/98

Location: Mubarke, Isfahan

www.msc.ir

3

Unloading and packaging perlite cool box CO unit

Client: Fan Avaran Petrochemical Complex

Project implementation period: 5 days

Start date: 3/22/98

Location: Mahshahr port

www.fnpcc.com

4

Charging 2400 barrels of catalyst and rasin ring of sulfuric acid reactor No. 2

Employer: Sarcheshme copper complex

Project implementation period: 6 days

Start date: 5/2/98

Location: Kerman source

www.scico.ir

5

Discharge and charge of HTS, LTS and SEC-REF reactors of ammonia unit 2

Employer: Razi Petrochemical Complex

Project implementation period: 12 days

Start date: 2/20/98

Location: Asaluyeh

www.razip.com

6

Discharge, discharge and charge 360 barrels of catalyst and ceramic sulfuric acid converter

Client: Hayan Chemical Engineering

Project implementation period: 6 days

Start date: 1/20/98

Location: Zanjan

www.tadbir-chemi.com

7

Industrial cleaning of material transfer units, lime, steelmaking and foundry

Client: Toka Concrete Company

Project implementation period: 1 year

Start date: 1/1/98

Location: Mobarake Steel Complex, Isfahan

www.msc.ir

8

Discharging and charging reactors of desulfurization unit

Client: Saba Steel Isfahan

Project implementation time frame: 3 days

Start date: 5/11/97

Location: Mubarke, Isfahan

www.msc.ir

9

Discharging and charging reactors of desulfurization unit

Client: Saba Steel Isfahan

Project implementation time frame: 3 days

Start date: 5/11/97

Location: Mubarke, Isfahan

www.msc.ir

10

Discharge of catalysts 480 tubes of reformer unit

Employer: Isfahan Mobarake Steel Complex

Project implementation time frame: 3 days

Start date: 1/8/97

Location: Mubarke, Isfahan

www.msc.ir

11

Discharging and charging methanol synthesis reactors (3 reactors including 14,397 2-inch tubes with a height of 7 meters)

Client: Fan Avaran Petrochemical Complex

Project implementation period: 7 days

Start date: 2/25/97

Location: Mahshahr port

www.fnpcc.com

12

 

Discharge of hydrogenation reactor under nitrogen conditions

Client: Fan Avaran Petrochemical Complex

Project execution time: 14 hours

Start date: 2/23/97

Location: Mahshahr port

www.fnpcc.com

13

Evacuation of preformer reactors under nitrogen conditions (2 reactors)

Client: Fan Avaran Petrochemical Complex

Project execution time: 18 hours

Start date: 2/22/97

Location: Mahshahr port

www.fnpcc.com

14

Unloading and packing the catalyst of the reformer tubes (588 4 inch tubes with a height of 14 meters)

Client: Fan Avaran Petrochemical Complex

Project implementation time frame: 34 hours

Start date: 2/20/97

Location: Mahshahr port

www.fnpcc.com

15

Filter document

Client: Maron Petrochemical Complex

Project implementation time frame: 1 day

Start date: 5/11/96

Location: Mahshahr port

www.mpc.ir

16

Evacuation of Perlite Coolbox reactors of CO unit

Client: Fan Avaran Petrochemical Complex

Project implementation time frame: 2 days

Start date: 10/27/96

Location: Mahshahr port

www.fnpcc.com

17

Evacuation of Perlite Coolbox reactors of CO unit

Client: Fan Avaran Petrochemical Complex

Project implementation time frame: 2 days

Start date: 10/27/96

Location: Mahshahr port

www.fnpcc.com

18

Emptying and cleaning the Open Drain channels and the propylene unit pond

Client: Maron Petrochemical Complex

Project implementation period: 20 days

Start date: 1/10/96

Location: Mahshahr port

www.mpc.ir

19

Unloading and packing of the catalyst and ceramics of the wings of the SRP unit

Employer: South Pars Gas Complex (Phases 2 and 3)

Project implementation time frame: 2 days

Start date: 9/25/96

Location: Asaluyeh

www.pogc.ir

20

Unloading and packing of the catalyst and ceramics of the wings of the SRP unit

Client: South Pars Gas Complex (Phase 1)

Project implementation time frame: 2 days

Start date: 9/20/96

Location: Asaluyeh

www.pogc.ir

21

Unloading, charging, loading and unloading, 1200 barrels of catalyst and ceramic wing of the sulfuric acid unit

Employer: Sarcheshme copper complex

Project implementation period: 7 days

Start date: 5/20/96

Location: Kerman source

www.scico.ir/FA

22

Draining the hydrocarbon sludge pond

Employer: South Pars Gas Complex (phases 17 and 18)

Project implementation time frame: 3 days

Start date: 9/29/95

Location: Asaluyeh

www.pogc.ir

23

Drain the dryer

Employer: liquefied gas complex 900 Gachsaran

Project implementation period: 5 days

Start date: 7/20/95

Location: Gachsaran

www.gsogpc.nisoc.ir

و...