Carried out projects
Title: Discharging and charging of sulfur unit reactors
Employer: Saba Steel Company of Isfahan
Time duration: 3 days
Start date: 2019 August 11
Place: Mobarakeh city of Isfahan province

Title: Overhauling of reformer unit: dischargiَng and charging of catalyst, fixing of dog legs, regulating of suspension systems, regulating of tube switches and, cleaning of tubes
Employer: Saba Steel Company of Isfahan
Time duration: 15 days
Start date: 2019 June 29
Place: Mobarakeh city of Isfahan Province

Title: Discharging and packaging of perlite cold box of CO unit
Employer: Fanavaran Petrochemical Company
Time duration: 5 days
Start date: 2019 June 12
Place: Bandar Mahshahr city of Khuzestan province

Title: Charging of catalyst of sulfuric acid reactor
Employer: Sarcheshmeh Copper Industries
Time duration: 6 days
Start date: 2019 April 25
Place: Shahrak Mes Sarcheshmeh of Kerman province

Title: Discharging and charging of catalyst of rectors of ammonia unit
Employer: Razi Petrochemical Company
Time duration: 12 days
Start date: 2019 May 10
Place: Asaluyeh city of Bushehr province

Title: Discharging, filtering, and charging of catalyst and ceramic of sulfuric acid converter
Employer: Tadbir Shimi Hayan
Time duration: 6 days
Start date: 2019 April 9
Place: Zanjan province

Title: Industrial cleaning of units of material handling, lime, steel making and casting
Employer: Touka Beton Company
Time duration: 1 year
Start date: 2019 March 21
Place: Mobarakeh city of Isfahan province

Title: Discharging and charging of rectors of sulfur unit
Employer: Saba Steel Company of Isfahan
Time duration: 3 days
Start date: 2019 January 25
Place: Mobarakeh city of Isfahan province

Title: Discharging and charging of catalyst of rectors
Employer: Pars Petrochemical Company
Time duration: 6 days
Start date: 2018 November 26
Place: Asaloyeh city, Bushehr province

Title: Discharging of catalyst of 480 tubes of reformer unit
Employer: Mobarakeh Steel Company
Time duration: 3 days
Start date: 2018 October 23
Place: Mobarakeh city of Isfahan province

Title: Discharging and charging of catalyst of methanol synthesis rectors
Employer: Fanavaran Petrochemical Company
Time duration: 7 days
Start date: 2018 May 15
Place: Bandar Mahshahr city of Khuzestan province

Title: Discharging of hydrogenation reactor
Employer: Fanavaran Petrochemical Company
Time duration: 14 hours
Start date: 2018 May 13
Place: Bandar Mahshahr city of Khuzestan province

Title: Discharging of preformer reactors
Employer: Fanavaran Petrochemical Company
Time duration: 18 hours
Start date: 2018 May 12
Place: Bandar Mahshahr city of Khuzestan province

Title: Discharging and packaging of catalyst of reformer tubes
Employer: Fanavaran Petrochemical Company
Time duration: 34 hours
Start date: 2018 May 10
Place: Bandar Mahshahr city of Khuzestan province

Title: Sand filtration
Employer: Marun Petrochemical Company
Time duration: 1 day
Start date: 2018 January 25
Place: Bandar Mahshahr city of Khuzestan province

Title: Discharging of reactors of CO unit
Employer: Fanavaran Petrochemical Company
Time duration: 2 days
Start date: 2018 January 17
Place: Bandar Mahshahr city of Khuzestan Province

Title: Discharging and packaging of perlite cold box of CO unit
Employer: Fanavaran Petrochemical Company
Time duration: 4 days
Start date: 2018 January 12
Place: Bandar Mahshahr city of Khuzestan province

Title: Discharging and cleaning of open drain channels and pond of polypropylene unit
Employer: Marun Petrochemical Company
Time duration: 20 days
Start date: 2017 December 22
Place: Bandar Mahshahr city of Khuzestan province

Title: Discharging and packaging of catalyst and ceramic of the SRP unit
Employer: South Pars Gas Company (Phase 2 and 3)
Time duration: 2 days
Start date: 2017 December 16
Place: Asaloyeh city, Bushehr province

Title: Discharging and packaging of catalyst and ceramic of the SRP unit
Employer: South Pars Gas Company (Phase 1)
Time duration: 2 days
Start date: 2017 December 11
Place: Asaloyeh city, Bushehr province

Title: Discharging, charging, filtering, and loading of catalyst and ceramic (1200 barrels) of sulfuric acid unit
Employer: Sarcheshmeh Copper Industries
Time duration: 7 days
Start date: 2017 August 11
Place: Shahrak Mes Sarcheshmeh of Kerman province

Title: Discharging of hydrocarbon sludge pond
Employer: South Pars Gas Company (Phase 17 and 18)
Time duration: 3 days
Start date: 2016 December 19
Place: Asaloyeh city, Bushehr province

Title: Discharging of dryer
Employer: Gachsaran Gas Company
Time duration: 5 days
Start date: 2016 October 11
Place: Gachsaran city, Kohgiluyeh and Boyer-Ahmad province