پروژه های شرکت زاگرس صنعت آرکا
Projects of Zagros Sanat Arka Company
Discharging and charging reactors of desulfurization unit
Client: Saba Steel Isfahan
Project implementation time frame: 3 days
Start date: 5/20/98
Location: Mubarke, Isfahan

Overhaul of the reformer unit includes: discharging and charging the catalyst, cutting and welding the doglegs, opening and closing the suspension systems, opening and closing the switch tubes, cleaning the tubes.
Client: Saba Steel Isfahan
Project implementation period: 15 days
Start date: 8/4/98
Location: Mubarke, Isfahan

Unloading and packaging perlite cool box CO unit
Client: Fan Avaran Petrochemical Complex
Project implementation period: 5 days
Start date: 3/22/98
Location: Mahshahr port

Charging 2400 barrels of catalyst and rasin ring of sulfuric acid reactor No. 2
Employer: Sarcheshme copper complex
Project implementation period: 6 days
Start date: 5/2/98
Location: Kerman source


Discharge and charge of HTS, LTS and SEC-REF reactors of ammonia unit 2
Employer: Razi Petrochemical Complex
Project implementation period: 12 days
Start date: 2/20/98
Location: Asaluyeh
Discharge, discharge and charge 360 barrels of catalyst and ceramic sulfuric acid converter
Client: Hayan Chemical Engineering
Project implementation period: 6 days
Start date: 1/20/98
Location: Zanjan


Industrial cleaning of material transfer units, lime, steelmaking and foundry
Client: Toka Concrete Company
Project implementation period: 1 year
Start date: 1/1/98
Location: Mobarake Steel Complex, Isfahan

Discharging and charging reactors of desulfurization unit
Client: Saba Steel Isfahan
Project implementation time frame: 3 days
Start date: 5/11/97
Location: Mubarke, Isfahan

Discharging and charging reactors of desulfurization unit
Client: Saba Steel Isfahan
Project implementation time frame: 3 days
Start date: 5/11/97
Location: Mubarke, Isfahan

Discharge of catalysts 480 tubes of reformer unit
Employer: Isfahan Mobarake Steel Complex
Project implementation time frame: 3 days
Start date: 1/8/97
Location: Mubarke, Isfahan

Discharging and charging methanol synthesis reactors (3 reactors including 14,397 2-inch tubes with a height of 7 meters)
Client: Fan Avaran Petrochemical Complex
Project implementation period: 7 days
Start date: 2/25/97
Location: Mahshahr port

Discharge of hydrogenation reactor under nitrogen conditions
Client: Fan Avaran Petrochemical Complex
Project execution time: 14 hours
Start date: 2/23/97
Location: Mahshahr port

Evacuation of preformer reactors under nitrogen conditions (2 reactors)
Client: Fan Avaran Petrochemical Complex
Project execution time: 18 hours
Start date: 2/22/97
Location: Mahshahr port

Unloading and packing the catalyst of the reformer tubes (588 4 inch tubes with a height of 14 meters)
Client: Fan Avaran Petrochemical Complex
Project implementation time frame: 34 hours
Start date: 2/20/97
Location: Mahshahr port

Filter document
Client: Maron Petrochemical Complex
Project implementation time frame: 1 day
Start date: 5/11/96
Location: Mahshahr port
www.mpc.ir

Evacuation of Perlite Coolbox reactors of CO unit
Client: Fan Avaran Petrochemical Complex
Project implementation time frame: 2 days
Start date: 10/27/96
Location: Mahshahr port
www.fnpcc.com

Evacuation of Perlite Coolbox reactors of CO unit
Client: Fan Avaran Petrochemical Complex
Project implementation time frame: 2 days
Start date: 10/27/96
Location: Mahshahr port

Emptying and cleaning the Open Drain channels and the propylene unit pond
Client: Maron Petrochemical Complex
Project implementation period: 20 days
Start date: 1/10/96
Location: Mahshahr port

Unloading and packing of the catalyst and ceramics of the wings of the SRP unit
Employer: South Pars Gas Complex (Phases 2 and 3)
Project implementation time frame: 2 days
Start date: 9/25/96
Location: Asaluyeh

Unloading and packing of the catalyst and ceramics of the wings of the SRP unit
Client: South Pars Gas Complex (Phase 1)
Project implementation time frame: 2 days
Start date: 9/20/96
Location: Asaluyeh

Unloading, charging, loading and unloading, 1200 barrels of catalyst and ceramic wing of the sulfuric acid unit
Employer: Sarcheshme copper complex
Project implementation period: 7 days
Start date: 5/20/96
Location: Kerman source

Draining the hydrocarbon sludge pond
Employer: South Pars Gas Complex (phases 17 and 18)
Project implementation time frame: 3 days
Start date: 9/29/95
Location: Asaluyeh

Drain the dryer
Employer: liquefied gas complex 900 Gachsaran
Project implementation period: 5 days
Start date: 7/20/95
Location: Gachsaran